DTE Energy Seeks Proposals for Up to 150 MW of New Michigan Solar

The solicitation, tied to a 2025 commission settlement, requires selected projects to be operating by mid-2030.

Mira KovalenkoNovember 22, 20265 min read1 views
A conceptual illustration of rows of ground-mounted solar panels on farmland, with transmission lines at the horizon, representing a planned 150-megawatt solar procurement.

DTE Energy plans to add up to 150 megawatts of new solar generation in Michigan and has opened a competitive solicitation to procure it, the company said. DTE said the move would create construction jobs, support local communities and save customers money on fuel costs.

Because solar generation does not require fuel, the company said the projects would help reduce its exposure to changing fuel prices over their operating lives. DTE also linked the procurement to its broader work to supply customers with energy that is reliable, increasingly clean and affordable. The announcement did not name specific project sites or selected developers, and the 150-megawatt figure represents a ceiling on the procurement rather than a finalized build.

Company casts projects as in-state investment

DTE characterized the projects as an investment in Michigan and its communities. By producing more Michigan-made energy that does not require the purchase of fuel, the company said, it can help lower energy costs for customers and reduce reliance on fuel from outside the state. DTE added that the projects would create jobs and bring new investment and tax revenue into local communities, providing more resources for schools, first responders and the services Michigan families count on.

Bidding terms tied to 2025 commission settlement

The procurement covers up to 150 megawatts of new Michigan-based solar generation and supports requirements of the settlement agreement in Michigan Public Service Commission Case No. U-21662, which was approved May 15, 2025. Under the terms DTE described, projects must achieve commercial operation by June 30, 2030, be located in Michigan, and connect to either the MISO transmission system or DTE's distribution system.

Interested bidders can register and obtain additional information through PowerAdvocate, according to the company. Proposals are due Jan. 19, 2027, and DTE expects to execute contracts in the second or third quarter of 2027.

One step in a larger renewable build-out

DTE describes itself as a producer of and investor in renewable energy in Michigan, generating enough clean energy from wind and solar to power nearly one million homes. The company said it remains committed to growing its renewable energy portfolio while maintaining a balanced mix of energy resources that supports reliability and affordability for customers as it works toward net zero carbon emissions. DTE's 2026 Integrated Resource Plan builds on that commitment, calling for an additional 15 gigawatts of renewable energy by 2042.

The 150-megawatt solicitation is one element of that longer-term build-out, though the company did not say how much of the 15-gigawatt target solar is expected to supply. DTE also did not indicate how many projects it expects to select or how the 150 megawatts would be divided among bidders.